Although official reports project will start construction in October, but by the beginning of October, has not yet started. This group photograph journalists surging bangs
Not really started, "special approval by the State Council" of zhaotong, Yunnan plans to build 700,000 tons of electrolytic aluminum projects, suddenly into a whirlpool of public opinion.
September 2015, zhaotong City Government signed a project framework agreement with Yunnan metallurgical group, indicating the project location, the scale of production as well as finalize. It was stated that the project has a total investment of 6 billion yuan.
However, as early as the two sides signed the framework agreement a few days ago, and signed it "zhaoyang District Environmental Protection Bureau" proposal suddenly wide spread on the Internet. "Proposal" says outlet location in the city, the project on urban and human influence, recommended construction of the selected address.
Zhaoyang district of zhaotong city, although belonging to the EPA sound "rumor", but the project's civil site questioning continues. Surging News (www.thepaper.CN) during the visit, many members of civil society on issues such as the location for this project were pessimistic.
At present, the project is still in the stage of EIA, the Zhao Yang industrial park, a staff member said: "EIA conclusion, after in November at the earliest. Now talk about environmental impact, would be premature. "
"Overcapacity" special projects
Local people believe that electrolytic aluminum projects would cause irreversible environmental impacts of Shaoyang city.
News of large electrolytic aluminum projects to be constructed, as early as the beginning of 2015 already in zhaotong, Yunnan local spread like wildfire.
Aluminum is widely used by industries such as light industry, electronics and metals, almost all the technological environment level obtained by electrolysis. At present, the domestic electrolytic aluminum projects faced serious over-capacity situation.
Under the guidance of the State Council on solving serious excess capacity contradiction, on April 20, 2015, the Ministry issued some overcapacity industry capacity replacement notification of implementation measures, "no new capacity of electrolytic aluminum industry. "
Or coincidence, issued notice 2 days later, zhaotong City Government and the Yunnan metallurgical group which held a forum to discuss "700,000 tons of hydro aluminum integrated project" related issues.
A local official to the press that the surging, the project of ludian County last year post-earthquake reconstruction projects, led by the Yunnan Provincial Government, special approval by the State Council, is "reconstruction support projects".
Zhaoyang district governments concerned in a surging news interview also confirmed that the project really "established special approval by the State Council. "
Several local politicians to press that the surging, the project launched expeditiously, in addition to the reconstruction of outside policy, zhaotong also requires that such local economic development projects "without further ADO."
Within the jurisdiction of zhaotong city, apart from the shuifu County, and remaining 10 counties and districts, including zhaoyang district are State-level poverty-stricken counties.
In the year 2015, zhaotong city officials requested a citywide "anti-poverty battle" to areas in all poverty before 2020. Surging more than local politicians to press quoted meeting requests: "deadline not poverty districts and counties, top leaders should be accountable. "
According to official estimates, plans to invest about 6 billion yuan of this major project will bring annual fiscal revenue of 5.6 billion yuan in zhaotong city.
"Such a major project, zhaotong city, on enormous significance. "A department-level officials to the press that the surging of zhaotong city.
EPA denies the "Devil's advocate"
In September this year for some unexpected "episode", and electrolytic aluminum projects instantly raised public attention.
On September 15, a signed "zhaoyang District Environmental Protection Bureau" proposal of heat transfer on the Internet.
"The proposal," said output of 700,000 tons of electrolytic aluminum project site in zhaoyang district du Jia Qing gang Ling Xiang Liang Zi Cun, due north of the city, zhaoyang district of the city, only 8 km line distance, zhaoyang district, a leading wind Northwest to North wind, "(item) of zhaoyang district greatly and zhaoyang district centre of urban pollution in the dam area, effects of fluoride on human skeleton is great, recommended construction of the selected address. "
Electrolytic aluminum projects are an important feature of pollution risks: its discharge of major pollutants "fluoride" cumulative emissions up to a certain value, direct impact on the surrounding soil, crops and human health project emissions of dust also affect the air.
"Recommendations" Maxed zhaotong locals in an instant "ring of friends", in addition to read are also forwarded to other friends.
Zhaoyang district, but the environmental protection agency denied that publish related content. On September 18, zhaoyang District Environmental Protection Bureau said in a statement on its website, and has never been released in any form any information about the project, "is being used on behalf of, police. "
"Certainly not official documents. We also very surprised to see this news, because such a big project, production is unclear, District Environmental Protection Bureau could not give a recommendation. "Surging Dragon named zhaoyang District Environmental Protection Bureau Director told the news. "And such practices, as well as general administrative rules. "
But a person familiar to the surging of environmental protection system in zhaotong News: "(the proposal) should be within the environmental protection agency, a preliminary opinion, because once the project is put into operation, monitoring, law enforcement, District Environmental Protection Bureau will take into account the subsequent pressure. " Chinese American woman student who was stabbed
Publicly reported, on September 21, zhaotong City Government signed a framework agreement with Yunnan metallurgical group, indicating the location, production scale has been finalized.
The report also showed that the location of electrolytic aluminum projects, networks that "advice" mentioned in the du issue.
"Waiting for the EIA results"
Du Jia Liang Zi behind Zhao Yang city, is known as the "mother River" of sayuhe.
Were waves of public opinion by pushing at the same time, there are projects where Zhao Yang industrial park.
Electrolytic aluminum projects down address zhaoyang district, located just north of the Green gang Ling Xiang du Jia Liang Zi Cun area.
Surge in local news survey found that, from the city to the city takes about half an hour's drive, and the mire by a 1 km trail. Du Jia Liang Zi villagers around less, seen from the topography, elevation higher than Shaoyang city.
Zhao Yang industrial park, according to the staff, according to the preliminary plan, electrolytic aluminum projects future area of 2100 acres, expropriation is mainly barren hills and woodlands, and a few farms, "Hill was leveled. "
Du Jia Liang Zi behind Zhao Yang city, is known as the "mother River" sayuhe, "it would supply the aluminum project of hydropower industry and domestic use. "A zhaoyang District Government officials said.
A Weather Bureau of zhaotong City staff member told the word news, zhaoyang district, prevailing wind direction is North-West of northerly winds.
Question says: why electrolytic aluminum project in the du issue on the air?
Zhao Yang industrial park, from planning, Qing gang Ridge area was zoned as industrial park mining and metallurgical processing base. "In accordance with the relevant provisions of this type of project must fall into the range of the base. "Zhao Yang industrial park, a staff member explained to the surging News said.
According to him, in the course of discussion, the siting of the project once had four options, but considered view that, du Jia Liang Zi is "right"
It is worth mentioning that, du Jia Liang Zi is not the first mining and metallurgy industry, ":".
Public reports indicate that originally planned in the town settled in the North Gate of the annual output of 100,000 tons of electrolytic zinc project, after relocation, originally to be settled in the du issue.
"Then to mount electrolytic aluminum projects, electrolytic zinc project gave way. "Zhao Yang industrial park staff.
Zhaotong, while media citing local officials reported that electrolytic aluminum projects will start in October, but as of October 8, du Jia Liang Zi signs does not start.
Zhao Yang industrial park, said a staff member surnamed Chen, the current EIA was submitted for approval, "the CMC noted that public doubts about the siting of this project a lot. Process data from the enterprise, little risk of pollution. All await the EIA conclusion after in November at the earliest. Now talk about environmental impact, would be premature. "